Construction Activity
Modernize 75 Map

Construction Progress

The Modernize 75: 2016 Segment is 48.1% complete as of May 29, 2017.

2017 Work

ROAD CONSTRUCTION

  • Northbound I-75 from Squirrel Road to north of South Boulevard
  • Southbound I-75 from Coolidge Highway to north of South Boulevard
  • Adams Road ramps to and from southbound I-75
  • I-75 Business Loop (Square Lake Road) ramps to and from I-75

BRIDGE CONSTRUCTION

  • Southbound I-75 bridge over Square Lake Road
  • Southbound I-75 bridge over Adams Road
  • I-75 Business Loop (Square Lake Road) interchange bridges

2017 Traffic Impact

  • Two lanes will be open in each direction on I-75
  • Motorists and area residents can expect limited nighttime and weekend freeway closures for bridge demolition and beam setting

2018 Work

  • Landscaping and tree replacements

2016 Work Completed

TEMPORARY CONSTRUCTION

  • Temporary crossovers and widening for maintaining traffic

ROAD CONSTRUCTION

  • Northbound I-75 from Coolidge Highway to Squirrel Road
  • Adams Road ramps to and from northbound I-75

BRIDGE CONSTRUCTION

  • Northbound I-75 bridge over Square Lake Road
  • Northbound I-75 bridge over Adams Road
  • Squirrel Road bridge over northbound and southbound I-75

2016/2017 construction along I-75 will include the segment north of Coolidge Highway to north of South Boulevard.

Planned Improvements

  • Reconfigure the I-75 Business Loop (Square Lake Road) interchange
  • Replace freeway lanes and bridges
  • Connect with Bloomfield Township Safety Paths on Squirrel Road over I-75
  • Develop and construct tree replacement and landscape plan
  • Upgrade existing Bloomfield - Adams Road Carpool Lot
  • Incorporate collaboratively-developed community aesthetics