Segment 2 North of 13 Mile to North of Coolidge Highway

Construction Progress to Date

56%

The I-75 Modernization Project within Oakland County - From M-102 to South Boulevard - is a mega project and being managed by an independent MDOT I-75 Team.

___________

For Segment 2 (North of 13 Mile Rd to North of Coolidge Hwy) questions or comments please reach us at: (313) 518-1078 or send an email to MDOT-I75-MegaProject@michigan.gov and include your contact information.

__________

Your questions will be answered as soon as possible. Thank you!

WEEKLY ALERTS

POSTED 11.26.19
11/18/2019-11/27/2019
Road Closures & Alternate Routes

Later in Evening: Wednesday, November 27th Northbound I-75 Exit Ramp to Rochester Opens!

Tomorrow in the evening, (Wednesday, November 27th) it is expected that crews will open the new, reconstructed, ramp for motorists.  This is weather dependent. Thank you for your continued patience as we try to wrap up this complex, and extensive construction project for the Winter season.

_____________

2019 Milestone for Segment 2 Delayed until Late December

Due to weather delays and additional work added to the original contract, switching northbound I-75 traffic to its pre-construction configuration has been delayed until later December.  Full press release.

______________

Later This Evening: Monday November 18th - Northbound I-75 Exit Ramp to Big Beaver Opens!

This evening (Monday, November 18th), it is expected that crews will open the new, reconstructed, ramp for motorists. This is weather dependent. Thank you for your continued patience during this complex and extensive construction project. 


MORE >

The Modernize 75 widening and reconstruction project has been in the planning and development stages for nearly 20 years. North of 13 Mile to North of Coolidge is under construction through the 2020 season, and Segment 3 began preparing the roadway in the fall of 2019.

THE LATEST

12.02.19

Project Info Placemat

View full size 

11.26.19

Pavement Removal and Replacement Needed on Portions of I-75

Crews will need to replace a half mile of two lanes of northbound I-75 from 13 1/2 Mile to 14 Mile roads and the shoulders on the exit ramps to Big Beaver and Rochester roads.  Pavement replacement on the exit ramp to Rochester Road has been completed.  Replacement on Big Beaver exit ramp and northbound I-75 will occur next year.  This will NOT impact the scheduled switching of northbound I-75 to its pre-construction configuration in late December.  Full press release.

11.26.19

Later In Evening: Wednesday, November 27th Northbound I-75 Exit Ramp to Rochester Opens!

Tomorrow in the evening, (Wednesday, November 27th) it is expected that crews will open the new, reconstructed, ramp for motorists.  This is weather dependent. Thank you for your continued patience as we try to wrap up this complex, and extensive construction project for the Winter season.

11.22.19

Saturday, November 23rd - Right Lane Closure on NB I-75

Tomorrow, Saturday November 23rd, from 7am to 7pm the right lane of northbound I-75 will be closed from 14 Mile Road to Maple Road. Crews will be milling and replacing asphalt in this section.  We apologize for the inconvenience.

11.20.19

2019 Milestone for Segment 2 Delayed until late December

Due to weather delays and additional work added to the original contract, switching northbound I-75 traffic to its pre-construction configuration has been delayed until later December.  Full press release.

11.18.19

Later This Evening: Monday, November 18th - Northbound I-75 Exit Ramp to Big Beaver Opens!

This evening (Monday, November 18th), it is expected that crews will open the new, reconstructed, ramp for motorists. This is weather dependent. Thank you for your continued patience during this complex and extensive construction project.